As reported by TxDOT: Due to weather delays, the traffic switch to Phase 2/3 is now scheduled to occur on March 2 and March 3
Lane closures:
• Southbound right lane from Westpark Drive to Winscott Road on Monday (2/29) and Tuesday (3/1) from 9:00am to 4:00pm both days for detour work.
• Various lanes will be closed on Tuesday/Wednesday in a moving operation for traffic striping north of Mercedes Street in Phase 3 of the project area.
• Various lanes will be closed on Wednesday/Thursday in a moving operation for traffic striping south of Sproles Drive in Phase 2 of the project area.
As always, please drive carefully and adhere to all traffic signs, as your safety is our first priority.